Cooper Farms: Wind Turbines

Port Clinton, Ohio


Mosser Construction’s scope of work included pouring the concrete foundations for the wind turbine project for Cooper Farms.

Construction of the two towers began in mid-September, with work on the foundations. The turbines were delivered in November, with installation completed December 30.  Following testing in January, the equipment was fully functioning by mid-February.

  • Two 1.5 megawatt wind turbines
  • Tower height of each tower is 421 feet
  • The turbines generate more than half of the plant’s energy needs.