One Energy LLC: Haviland Plastic Products Wind Farm
Haviland, Ohio
Mosser Construction’s scope of work included pouring the concrete foundations for the wind turbine project at Haviland Plastic Products. This project included three Goldwind 1.5 MW wind turbines, producing 4.5 MW a month. These wind turbines help offset Haviland Plastics’ power consumption and save them hundreds of thousands of dollars a year while also significantly reducing their long-term energy costs.
- A total of 1,000 yards of concrete was poured for three turbine foundations
- 100 tons of resteel were laid for the three foundations